project plan/schedule

The entire project must be finished by the 26th of April 2006 at the latest. So I have generated a roadmap to meet this deadline in an effective and efficient manner. Using the ordered task list from the previous page (which contained all the tasks—broken down into subtasks where necessary) I allocated a realistic amount of time to complete each, and then continued to spread them over the five week time period. I then built-in special contingency days at the end of each significant stage (milestone) in the project cycle, except I decided to merge the Design and Implementation stages into one block because they are so inter-related.

I have split up the schedule into weeks to provide me with a clearer understanding of the volume of work that needs to be done. As a Christian I will not be working on the first day of the week (Sunday) because I regard it as a day of rest from work to celebrate Christ's resurrection victory over sin, death and hell and to hear the word of God preached.

On the last day of each week I will write a progress report; in total there will be four of these. I will also use this time to make effective use of the plan to monitor my progress.

Below is my project roadmap:

Stage in cycle   Task/subtask name   w/c 26-Mar   w/c 02-Apr   w/c 09-Apr   w/c 16-Apr   w/c 23-Apr
Investigation   Plan interview   01-Apr (1hr)           
-   Interview PSD partners   01-Apr (1hr)                
-   ¬ Analysis of interview   01-Apr (2hrs) WPR*              
-   Evaluation of similar website       03-Apr (4hrs)            
-   End-user survey       03-Apr (2dys)            
-   ¬ Analysis of results       06-Apr (1hr)            
-   Overall requirements       06-Apr (3hrs)            
-   ¬ List of goals       06-Apr (1hr)            
Contingency allowance (07-Apr)
Design   Website branding       08-Apr (2hr) WPR*          
-   Content explanation           10-Apr (2hrs)        
-   Structure and navigation           10-Apr (2hrs)        
-   Accessibility and Style           10-Apr (2hrs)        
-   Initial design           11-Apr (2hrs)        
-   Story boards           11-Apr (4hrs)        
Implementation   Dev process explanation           12-Apr (1hr)        
-   1st prototype (ver 1.0)           12-Apr (4hrs)        
-   PSD questionnaire           12-Apr (1hr)        
-   ¬ Analysis of feedback           13-Apr (1hr)        
-   ¬ Document changes           13-Apr (2hrs)        
-   2nd prototype (ver 2.0)           13-Apr (2hrs)        
-   End-user questionnaire           14-Apr (1hr)        
-   ¬ Analysis of feedback           14-Apr (1hr)        
-   ¬ Document changes           14-Apr (2hrs)        
-   Complete website (ver 3.0)           14-Apr (2hrs) WPR*      
Contingency allowance (15-Apr)
Testing   Test plan               17-Apr (1hr)    
-   Test log               17-Apr (2hrs)    
-   ¬ W3C XHTML validation               17-Apr (0hrs)    
-   Document changes               17-Apr (2hrs)    
-   End-user questionnaire               17-Apr (1hr)    
Contingency allowance (18-Apr)
Evaluation   Goals met?               19-Apr (2hrs)    
-   Questionnaire results               19-Apr (2hrs)    
-   Improvements               19-Apr (2hrs)    
Contingency allowance (20-Apr)
Proposal   Research               21-Apr (1hr)    
-   ¬ Functionality write up               21-Apr (2hrs)    
-   ¬ E-commerce write up               21-Apr (2hrs) WPR*  
Contingency allowance (22-Apr)
Contingency allowance (24-Apr)
Contingency allowance (25-Apr)
DEADLINE   -                   26-Apr-2006

* Weekly progress reports.

Click next to view the weekly progress reports...